Shea Stadium

On January 3, 2003 we were awarded the contract to remove, replace and retrofit the existing left field bleachers. Work was completed in less than 3 months in time for the March 30, 2003 opening day deadline. In the ensuring 3 months, we poured 300 yards of concrete in one of the coldest winters on record, designed, fabricated and erected new steel bleacher systems. Related work included modifying the left field wall with inclusion of vision panels, construction of a handicapped seating viewing section underneath the bleacher systems, construction of a 25′ high handicapped lift, miscellaneous railings, paving and an adjacent picnic area.